Second USAID Contractor Suspended Following Caracol Housing Debacle Print

Caracol Flood houses
Image from internal USAID document, caption reads: “Site flooding due to improper drainage”

On March 25, 2015, USAID suspended CEEPCO Contracting – which had been working on shelter programs in Haiti –from receiving further government contracts, pending the outcome of an ongoing investigation. CEEPCO joins Thor Construction, which was suspended in early February. The investigation concerns faulty construction practices related to 750 houses built in Caracol, Haiti by USAID. CEPR Research Associate Jake Johnston reported in February for VICE News:

CEEPCO's CEO is Harold Charles, a Haitian-American who was formerly one of the Haitian government's representatives to the Interim Haiti Reconstruction Commission (IHRC), run by Bill Clinton and meant to be in charge of the $10 billion in earthquake relief. The IHRC had initially approved the USAID shelter program back in December 2010.

Charles also enjoys a close, personal relationship with Haitian President Michel Martelly. In an interview in 2013, Charles said, "I do know and have very close friends up through the highest ranks of government," adding, "Martelly is a childhood friend of mine." One former government official in Haiti said in an interview, "this was seen as a deal that would please Martelly."

Despite the initial assessment in August, 2014 that revealed the construction problems, USAID extended CEEPCO's contract for work at other shelter sites in Haiti this past January. CEEPCO’s contract for the Caracol site was awarded without competition. A Freedom of Information Act (FOIA) request for the justification document is ongoing. A FOIA request for the initial assessment documenting the problems with the houses was recently responded to, but USAID withheld the entire document that was sought, citing the ongoing legal investigation.

Though the investigation continues, many thousands of Haitians continue to live in the poorly constructed houses. A contracting document from November, 2014, stated that repairs must be “carried out immediately in order to prevent possible harm to residents.” But it is unclear if meaningful remediation efforts have taken place.  An internal document reveals that many of the identified problems would require serious structural work to the houses.

In November, Tetra Tech, another U.S.-based firm, received a $5 million contract to oversee the repair efforts. The firm has been performing structural evaluations of the houses in anticipation of a future legal suit. One draft document, prepared by Tetra Tech and obtained by HRRW, details 29 instances “of material substitutions, field design changes, lack of quality assurance/quality control (QA/QC) and lack of quality workmanship.”

Read more...

 

 
CEP Proposes Electoral Calendar During Meeting with Political Parties Print

During a meeting yesterday at the Hotel Karibe Convention Center, the CEP presented a draft electoral calendar to political parties present. The proposal would have the first round of legislative elections on August 9, the second round of legislative elections and first round of presidential elections on October 25 and finally the second round of presidential elections and local elections on December 27. The electoral decree, which provides the legal basis for the election, was approved by the president on March 2.

A key date in the electoral process will be March 23, when the CEP will publish the list of registered political parties. Registration will open on March 16 and parties will have 5 days to register. This will be looked at as a key indicator of the inclusiveness of elections, as in past elections key political parties have been excluded from participation.  Some opposition political movements were not present at yesterday’s meeting, including MOPOD, RDNP and Petit Dessalines, according to Alterpresse. For his part former Senator Moise Jean Charles of Petit Dessaline explained they would not attend, “…because conditions have not been met. The electoral environment is part of the context of the crisis.”

INITE, which joined the Martelly government as part of a political deal in January, was supportive of the proposed calendar. Paul Denis expressed his party’s support for the holding of three elections, while adding that some continue to not want elections at all. “No one should come with pretexts for not organizing elections so as to generate trouble in the country,” he said. In an interview with Le Nouvelliste, former INITE Prime Minister Jean-Max Bellerive indicated his intention to run, at some level, in the elections.

Fanmi Lavalas and Fusion both expressed concern with the calendar, preferring to have the election in two-rounds as opposed to three. Le Nouvelliste reported that according to Dr. Louis Gérald Gilles of Lavalas, “neither political parties nor the country will have the necessary economic resources to participate in an electoral process that stretches from March 16 to December 27 2015.” Lavalas was excluded from participating in the 2010 elections. In an interview earlier this week with the Haiti Press Network, Prime Minister Evans Paul stated that, “an important sum will be made available to the various political organizations to run in the presidential elections.”

While there are concerns over the proposed timetable, the bigger issue appears to be in the formation of the Bureaux electoraux départementaux (BED) and Bureaux electoraux communaux (BEC). These institutions play a key oversight role as their members are responsible for communal and departmental dispute resolution. According to Le Nouvelliste, “Most political parties considered that the CEP should have first resolved the issue of the members of the BEC and BED before focusing on the electoral calendar.”  Gilles of Lavalas added that, “the BED and BEC constitute the basis for credible elections in the country.”

In response to the questions raised about the BED and BEC, Nehemy Joseph, a member of the CEP, stated they lacked control over financial resources and were unable to travel the country and ensure that the local institutions are being formed properly. In an interview with Le Nouvelliste, the head of the United Nations Development Program (UNDP), Sophie de Caen, announced that the electoral fund had over $38 million at its disposal. But, while the Haitian government is the largest single contributor, control of those funds rest with the international community and the UNDP in particular. Le Nouvelliste reported that, “certain political party leaders have roundly denounced the fact that the UNDP controls more than $38 million for the country’s elections, while the relevant body for the organization of elections, the CEP, functions with very limited economic resources.”

A final decision on the electoral calendar will be made in the coming days. 

 
USAID Contractor Suspended as Investigation into Faulty Houses in Haiti Continues Print

CEPR Research Associate and lead HRRW blogger, Jake Johnston, published the following piece on VICE news today:

After the devastating earthquake that hit Haiti in January 2010, the US government responded with an ambitious plan to build 15,000 new houses in the country. But the ensuing program to put roofs over the heads of displaced Haitians has included a boondoggle of epic proportions at one $35 millionhousing development, where shoddy construction practices and faulty sewage systems are currently the subject of an ongoing investigation.

On February 3, the US-based company Thor Construction was suspended from receiving government contracts because of its work in Haiti. Another contractor with close ties to the Haitian president has so far escaped punishment.

As the relief effort's flagship housing project comes under increased scrutiny, interviews with involved parties and an analysis of contract documents, independent reports, and congressional testimony reveals that the problem is far from a simple case of contractor malfeasance. Rather, USAID, the government agency responsible for administering foreign civilian aid, simply failed to provide meaningful oversight of its contractors and ensure adequate results for US-taxpayer financed projects.

In April 2012, Thor received $18.4 million to build 750 houses at a site on Haiti's northern coast called Caracol-EKAM, part of the international community's high-profile reconstruction project at the Caracol Industrial Park. At a star-studded inauguration of the park in October 2012, then Secretary of State Hillary Clinton toured the new buildings and spoke of "affordable homes with clean running water, flush toilets, and reliable electricity... built to resist hurricanes and earthquakes."

In June 2013, the Government Accountability Office (GAO) found that the initial target of 15,000 total houses in Haiti had been reduced to just 2,600 while at the same time costs increased from $53 million to more than $90 million. USAID Assistant Administrator Beth Hogan explained to Congress that the high costs were "because of the requirements" that the contractor "meet international building codes, that it comply with federal building standards," and "that these materials would be disaster- and hurricane-proof." Hogan added that she was "very happy with the quality" of the houses.

But a year and a half later, Hogan's story is coming apart at the seams. In November, USAID awarded a $5 million no-bid contract to US-based Tetra Tech to provide remediation services for the Caracol houses. An independent assessment conducted in August 2014 "revealed numerous deficiencies," with the houses, including roofs not being fastened, use of "sub-specification" materials, and "other structural and drainage issues," according to a contract document. Given the location's susceptibility to hurricanes and other extreme weather events, the document noted repairs must be "carried out immediately in order to prevent possible harm to residents."

Read the rest here. For more background, see here, here and here.

 
Ban Ki-moon Explains to Congress Why the UN Won’t be Held Accountable for Cholera in Haiti Print

In December, Rep. John Conyers and 76 other members of congress wrote to United Nations Secretary General Ban Ki-moon, urging the U.N. to provide a settlement mechanism for cholera victims and their families and lays out the reasons why the UN should be legally obliged to provide such a mechanism.  The members of Congress add that, “while we applaud the UN’s efforts to secure more funding for cholera treatment….we wish to respectfully remind you that these efforts do not absolve the UN of its obligation to receive legal claims from victims of the epidemic and provide remediation for the affected communities.” 2 months later, Ban Ki-moon has finally sent the members of Congress a lengthy response which the defenders of Haiti’s cholera victims have characterized as “untenable as a matter of law and logic.”

In a letter, dated February 19, 2015, Ban Ki-moon responds to the 76 members of congress. Most of the letter is dedicated to outlining all the work the U.N. has done to combat cholera in Haiti.  The U.N. has indeed issued calls for cholera funding, but the Haitian government’s 10-year cholera eradication plan remains woefully underfunded. Just 18 percent of the $2.2 billion required has thus far been pledged, with less than 13 percent actually disbursed, according to the most recent data [PDF]. A donor conference in October failed to secure significant additional pledges of support.

Only at the end of the letter does Ban actually respond to the members of Congress’ request for a settlement mechanism for the victims of cholera.  After initially rejecting the claims of the victims in a terse statement with little explanation, Ban provides perhaps the most thorough explanation to date for why the U.N. will not hear the claims:

Claimants invoked Section 29 of the Convention on the Privileges and Immunities of the United Nations of 1946 (the "General Convention") and paragraph 55 of the Status of Forces Agreement (SOFA) with the Government of Haiti, which implements Section 29(a) of the General Convention in the agreement with Haiti.

Section 29(a) is limited by its terms to the consideration of private law claims.  In the practice of the Organization, disputes of a private law character have been understood to be disputes of the type that arise between private parties, such as, claims arising under contracts, claims relating to the use of private  property in peacekeeping contexts or claims arising from motor vehicle accidents. The Organization has regularly received and provided compensation for such claims arising out of acts attributable to its peacekeeping missions and personnel.

I wish to assure you that, in the present case, the claims were thoroughly and carefully considered. After a review of the claims and the history and implementation of Section 29(a) of the General Convention, the claimants were informed that the claims were not receivable pursuant to Section 29 of the General Convention. As the claims in question raised broad issues of policy that arose out of the functions of the United Nations as an international organization, they could not form the basis of a claim of a private law character and, consequently, the claims did not fall within the scope of Section 29(a) of the General Convention. For the same reason, it was determined that these claims were not of the type for which a claims commission is provided under the SOFA, since the relevant provision of the SOFA also relates to claims of a private law character.

To read Ban’s full response, click here. Unfortunately, while this may be the most words a U.N. official has said about the legal case, it leaves much to be desired. Bruce Rashkow, a former high-ranking official in the U.N.’s Office of Legal Affairs wrote last year that the U.N. stance that cholera claims were “not receivable” was unprecedented. “Indeed, as the head of the UN legal office that routinely handled claims against the Organization for some ten years, I did not recall any previous instance where such a formulation was utilized in regard to such claims,” Rashkow wrote.

The Institute for Justice and Democracy in Haiti, which is representing Haitian cholera victims in their legal battle, provided the following response to Ban’s letter:

The Secretary-General’s assertion that the claims of Haiti’s cholera victims are an exception to the UN’s legal obligation to compensate people harmed by its negligence is untenable as a matter of law and of logic.  The Secretary-General fails to cite a single authority supporting the view that the cholera claims are not “disputes of a private law character.”  To the contrary, dozens of the world's leading experts in international law -- including many who have held positions in the UN -- have reviewed the cholera victims’ claims against the UN in conjunction with the UN's legal obligations. These experts agree that the cholera claims are private law claims, and that the UN had an obligation to settle them. The experts’ findings have been presented in a vast number of legal blogs, court briefs, and media articles, and are as applicable today as they were when the UN first dismissed the claims.

Read more...

 

 
On a Technicality, World Bank Rejects Complaint on Support for New Mining Law Print

A complaint from Haitian communities and supported by New York University’s Global Justice Clinic and Accountability Counsel has been rejected by the World Bank on technical grounds. The groups had asked for the Bank’s Inspection Panel to review whether assistance the Bank is providing to the Haitian government follows Bank guidelines relating to transparency and environmental safety.

Since 2013, the World Bank has provided technical assistance to the Haitian government in rewriting its mining laws, leading to a new mining law being drafted in 2014. Though Haiti has not seen large-scale commercial mining for decades, the government awarded multiple concessions in 2012 over opposition protests. In 2013, following a forum on mining sponsored by the World Bank, then Prime Minister Laurent Lamothe declared that to advance Haiti’s development, “we are counting heavily on the contribution of the mining sector.”

The Haitian communities’ complaint [PDF] states:

Complainants fear that, due to the government’s weak capacity and the law’s inadequacies, this increased investment in the mining sector will result in serious social and environmental harms, including contamination of vital waterways, impacts on the agriculture sector, and involuntary displacement of communities. Complainants are also concerned about the exclusion of Haitian people from the law reform process, particularly when contrasted with the reported regular participation of the private sector in drafting the new law. Further, Complainants fear that the government of Haiti lacks the capacity to regulate and monitor mining company activity.

In its response, the World Bank’s Inspection Panel says that it “has decided not to register the case.” The Panel acknowledged that the issues raised were “serious and legitimate,” and agreed that the new mining law could “have significant and considerable adverse environmental and social consequences.” However, because the World Bank support was provided through a technical assistance mechanism, “policies and procedures applicable to design, appraisal and implementation of a project, including the safeguard policies, were not applied to the Haiti Mining Dialogue.” The mechanism is not subject to the World Bank’s safeguard policies and therefore the Inspection Panel refused to hear the complaint.

Read more...

 

 